CHROME RECOVERY PLANT:

..

Completion Date


December 2015

Service Costs


..
R 580 100,00
..

Location


Illitha Mine Rustenburg

Services Performed


..

Design, Drawings, Procurement and Project Management:

  • Civil Specifications
  • Hopper and tank civil design
  • Ball Mill design (bunded area and surface bed)
  • Screens design (bunded area and surface bed)
  • Gravity Shake Tables design (bunded area and surface bed)
  • Conveyor bases design
  • Stormwater plan
  • Issuing of RFQ (Bulk Earthworks & Civil)
  • Bid evaluation
  • Awarding of the civil construction contract
  • Civil Contractor Supervision