CHROME RECOVERY PLANT:
Completion Date
December 2015
Service Costs
R 580 100,00
Location
Illitha Mine Rustenburg
Services Performed
Design, Drawings, Procurement and Project Management:
- Civil Specifications
- Hopper and tank civil design
- Ball Mill design (bunded area and surface bed)
- Screens design (bunded area and surface bed)
- Gravity Shake Tables design (bunded area and surface bed)
- Conveyor bases design
- Stormwater plan
- Issuing of RFQ (Bulk Earthworks & Civil)
- Bid evaluation
- Awarding of the civil construction contract
- Civil Contractor Supervision